All things being equal the multi-million dollar Ghana Gas Plant Project being construction at the Atuabo in the Ellembele District in the Western Region will be completed by the end of the year.
The Chief Executive Officer of the Ghana Gas Company, Dr George Sipah -Yankey made this know when he conducted media personnel round some aspect of the project at Atuabo and Sanzule also in the Ellembele District .
He said 90 per cent of the 110 kilometer gas pipeline from Atuabo to Aboadze in the Shama District has been completed while about 50 per cent of the entire project has been done.
Dr Sipah Yankey said by the end of next month all equipment for the project would have arrived adding that all financial challenges for the enterprise have been cleared.
Source: GBC