Ghana Gas Begins Compensation Pay-Outs Monday

As part of the Early Phase Gas Infrastructure Project from Essiama to Prestea, the Ghana National Gas Company (Ghana Gas) is undertaking another compensation payment exercise in the Western Region, effective March 30, 2015.

A total sum of about ₵7.8 million would be paid as part of the compensation package for crops, belonging to about 800 project-affected farmers in 23 communities along the Essiama-Prestea Lateral Line.

Beneficiary communities include Prestea, Banaho, Gwira Bibini Nsuaem, Kutokrom, Mbease Nsuta, Anyinam, Bondae, Ahomkakrom, Abrodiem, Wiawso, Esamzam, Ma Nyame Hunu, Bokazo, Krobo Junction, Eshiem, Tumentu, Dwira Semtum, Assuawaah, Angedware,
Atabobo, Aluka, Teleku Bokazo and Essiama. Procedures for crops compensation claims are as follows.
- Claimants must come to the compensation grounds with their original Form Fs issued
to them by the Lands Valuation Division (LVD) during the enumeration of the crops.

- Payment will only be effected upon receipt of the Form F, which will be used as
evidence of the entitlement of the claimant to the compensation.

- For the avoidance of doubt, all claimants around the Essiama end of the EP Line
would have their compensation claims handled at the Essiama Palace, whereas those
around the Prestea end of the line would have their claims handled at the Anyinam
Community Centre.

Ghana Gas also wishes to announce that it is ready to pay compensation for lands
compulsorily acquired for the Western Corridor Gas Infrastructure Development Project.
Ghana Gas is, however, awaiting directives from the Lands Commission with respect to the
validated beneficiaries of land compensation. We, therefore, urge claimants to the lands in
question to adhere to the following processes to expedite the process of payment to them.

- Claimants of land compensation are expected to make claims to the Lands
Commission within six months of the publication of compulsory acquisition notices in
the national dailies.

- The said compulsory acquisition notices in this case were published in August 2014.

- Upon validation of uncontested claims by the Lands Commission, Ghana Gas will be
obliged to pay the compensation to the claimant.

Ghana Gas, therefore, appeals to affected claimants to exercise patience while they go
through the validation process of the Lands Commission.

We appeal to claimants who may have difficulties in preparing their claims to contact the
offices of Ghana Gas for assistance. Officials are ready to assist them to the best of their
abilities.

ALFRED OGBAMEY
CORPORATE COMMUNICATIONS MANAGER
GHANA GAS (0302-744200)