Work On Achimota-Mile 7 Road To Be Completed by June - Contractor

Work on the Achimota-Mile 7 portion of the 5.7 kilometre Achimota-Ofankor road is expected to be completed by June this year. The project that was awarded to China Railway Wuju Group (CRWG) in 2006, at an estimated cost of GH�40 million to be constructed within 36 months, has delayed due to lack of funds the re-designing which has increased the contract sum by 375 per cent to GH�128 million.

 